ISO 14644-1:2015 · ASHRAE TC 9.9
Particle count testing and cleanroom classification
Airborne particle surveys for data halls, MMRs, UPS and battery rooms, and ISO-classified cleanrooms. Used for annual compliance, post-cleaning verification, and pre-IST handover after construction.
Why data centres count particles
Servers pull large volumes of room air through their chassis. Fine dust settles on heat sinks and fans, raising component temperatures. Some dust is worse than others: zinc whiskers shed from old galvanised raised-floor tiles are conductive, and dust carrying salts or sulfates absorbs moisture once room humidity passes its deliquescence point, which can cause leakage currents and shorts.
ASHRAE TC 9.9 therefore asks that data centres stay at ISO 14644-1 Class 8, with MERV 8 filtration on recirculated air and MERV 11 or MERV 13 on outdoor air. A particle survey tells you whether your filters, pressurisation and cleaning are holding that line.
How we run the survey
- Occupancy state agreed first. As-built, at-rest or operational, recorded on the certificate, because the same room gives very different counts in each.
- Locations from Table A.1 of ISO 14644-1:2015, based on floor area, then marked on your layout drawing with a location ID.
- Sample volume calculated so that at least 20 particles would be counted at the class limit for the largest particle size considered, with a minimum of 2 litres and 1 minute per sample.
- Pass per location. The 2015 edition dropped the 95% upper confidence limit calculation. Every location must meet the limit on its own.


ISO 14644-1:2015 class limits
Maximum particles per cubic metre of air, for particles equal to or larger than the stated size.
| ISO class | ≥ 0.3 µm | ≥ 0.5 µm | ≥ 1.0 µm | ≥ 5.0 µm | Typical use |
|---|---|---|---|---|---|
| Class 5 | 10,200 | 3,520 | 832 | n/a | Aseptic zones, semiconductor |
| Class 6 | 102,000 | 35,200 | 8,320 | 293 | Electronics assembly |
| Class 7 | n/a | 352,000 | 83,200 | 2,930 | Pharma secondary, DC handover (some operators) |
| Class 8 | n/a | 3,520,000 | 832,000 | 29,300 | Data centre white space (ASHRAE) |
| Class 9 | n/a | 35,200,000 | 8,320,000 | 293,000 | Ambient-controlled rooms |
Source: ISO 14644-1:2015, Table 1. "n/a" means the standard does not set a limit at that size for that class.
What your report contains
- Floor plan with every sample location and its ID
- Raw counts per channel, sample volume and timestamp for each location
- Pass or fail per location against the class you specified
- Instrument serial numbers, calibration dates and certificate references
- Observations: open floor tiles, missing blanking panels, door seals, construction debris
- Recommended actions and a suggested re-test interval
Most operators test every 6 or 12 months, and always after construction work, a filter change programme or a deep clean.